18' × 18' × 4' H

Sheet ID 18x18x4 matches the ID printed on your crate or QR code.

Frame

6′6′6′6′6′6′4′ RT20018′ per side4′1243

Swipe the drawing to see the full side.

18′ per side4′ high2 mid posts per side

Parts key

Corner connector: HW-RT200-C3W
1 Corner connectorHW-RT200-C3W · ×83-way corner piece
Straight splice: HW-RT200-S180
2 Straight spliceHW-RT200-S180 · ×16joins two RT200 tubes
Bottom support connection: HW-1420-0250-BH + HW-1420-BN · ×8
3 Bottom support connectionHW-1420-0250-BH + HW-1420-BN · ×8locks each mid post to the bottom rail
Tube adapter + mid post: RT150-43 ×8 · HW-RT150-TA ×16
4 Tube adapter + mid postRT150-43 ×8 · HW-RT150-TA ×16RT150 post with threaded tube adapters
RT200-696′ RT200RT150-434′ RT150 mid post

Need larger views? Open the connection pictures sheet.

Parts per frame

SKUDescriptionQty
HW-1420-0075-EB¼"-20 Eyebolt .75" Long4
HW-1420-0125-TS¼"-20 Thumb Screw 1.25" Long48
HW-1420-0150-FH¼"-20 Flat Head Screw 1.50" Long24
HW-1420-0250-BH¼"-20 Button Head Screw 2.50" Long8
HW-1420-0250-EB¼"-20 Eyebolt 2.50" Long8
HW-1420-BN¼"-20 Threaded Barrel Nut72
HW-RT150-TA1.50" Tube to 2.00" Tube Threaded Adapter16
HW-RT200-C3W2" Round Tube 3-way Corner Connector8
HW-RT200-S1802" Round Tube Straight Splicer16
RT150-43Aluminum Round Tube 43" Long8
RT200-452" Aluminum Round Tube 45" Long4
RT200-692" Aluminum Round Tube 69" Long24
Build order
  1. Build the top frame.
  2. Build the bottom frame.
  3. Add the vertical RT200 pieces.
  4. Add the RT150 mid posts.
  5. Square the frame and tighten every connection.
  6. Add graphics.
Rig and hang per venue requirements. Weight limits and rigging hardware are job-specific. Need replacement parts or graphics? Use the FastFrames planner.